Kaleshwaram Project Chief Engineer N Venkateshwarlu told
'Telangana Today' that there would be another 10,000 cubic metres of the
concrete pour from 8 am on Saturday to 8 am on Sunday.
Hyderabad: The mega concrete
pour at Medigadda barrage of the Kaleshwaram Lift Irrigation Scheme (KLIS),
which turned out to be a continuing saga, has set an all time record. Commenced
at 8 am on December 22, the men and machines that have been engaged in exercise
continued to work in shifts. The Kaleshwaram Project Chief Engineer N
Venkateswarlu informed Telangana Today that 90,055 cubic metres of Reinforced
Cement Concrete (RCC) was laid on the Medigadda barrage spill way and its
piers. One more day of work would take it to one lakh cubic metres, which is a
record in itself.
He said 16,722 cubic metres of
concrete pour was done on the first day. On an average, about 7,000-8,000 cubic
metres of concrete pour was being done every day. He explained that over lakh
cubic metres of concrete pour was yet to be done on the barrage, one of the six
important works need to be completed by March 2019 to commission the project
for giving water to the ayacut from next kharif. As desired by the Chief
Minister K Chandrashekhar Rao implementation of the project works has been put
on fast track. Undeterred by the cold wave sweeping across the State, men and
machines have been carrying out their work even under flood lights.
Referring to a similar exercise
taken up by the AP irrigation authorities at Polavarm project eying entry into
Guinness Book of World Records, he said they could be aiming at record for
maximum concrete pour in 24 hours. At Kaleshwaram, it will be a continuous
process till the remaining four lakh cubic metres of concrete pour was
completed. It may take less than a month to complete the concrete work. “We are
also awaiting observers of the Guinness Book of World Records. With a
deployment of 5000 men and engineers on the work site, we have ample scope to
break every record in the concrete laying history,” he asserted.
A total of 4,825 engineers and workers toiled for 72
hours to create a world record in non-stop concrete pouring at the Medigadda
barrage, a key component of the prestigious Kaleshwaram Lift Irrigation Scheme
(KLIS) that is expected to change the landscape of Telangana State.
Project Chief Engineer N Venkateswarlu told Telangana
Today on Tuesday that 25,583 cubic metres of Reinforced Cement Concrete (RCC)
was poured continuously to construct the spillway and piers at the Medigadda
barrage, starting 8 am on Saturday and ending at 8 am on Tuesday. Medigadda
barrage is one of the three key structures being constructed as part of the
KLIS to lift 2 tmc of water a day from the Godavari river.
The previous
record was held by a Dubai-based engineering company which completed 21,580
cubic metres of concrete pour over a period of 35 hours and 19 minutes for a
raft foundation laid for a residential complex from May 18 to 20 in 2017. The
Kaleshwaram project authorities who were successful in breaking this record,
however, should be a disappointed lot since they had not alerted the officials
of the Guinness Book of World Records to document the event. But, they are
confident of getting into the record books with yet another attempt at mega
concrete pouring in the near future.
The Medigadda barrage, coming up with 85 crest gates
and 16.17 tmc of water storage, will support an integrated irrigation system
intended to extend irrigation to 18,50,000 acres of new ayacut and stabilizing
almost the same extent of existing ayacut under Sriramsagar and other
irrigation projects. The mega effort, an unplanned event, was spurred by Chief
Minister K Chandrashekhar Rao, who after a marathon review meeting with
irrigation department officials last week, directed them to step up the pace of
works in various irrigation projects across the State. As desired by him, the
pace of works was stepped up in different packages of KLIS simultaneously.
The concrete laying that started routinely on the
spillway and piers of the Medigadda barrage at 8 am on Saturday achieved 16,722
cubic metres by 8 am on Sunday, which in itself was considered as the second
highest work turnout in concrete laying. Another 4,745 cubic metre of concrete
was laid on the second day and 4,177 cubic metres on the third day ending at 8
am on Tuesday. The network turnout was 21,100 cubic metres in 42 hours, 22,666
cubic metres in 62 hours and 25,583 cubic metres in 72 hours.
The Chief Minister laid the foundation stone for
Medigadda barrage on May 2, 2016. The barrage, as well as the pump houses,
would be ready by March 2019. The State government is keen on giving water from
the lift irrigation scheme to the ayacut from the next Kharif season.
No comments:
Post a Comment